In the Brandon Sun:
Power line to U.S. ‘ill-advised’ for Manitoban rate-payers: Pallister
Thursday, Mar. 13, 2014 at 2:08 PM
He said experts to testify at the ongoing PUB hearing will say Hydro’s expectations are overblown.
In the Brandon Sun:
Power line to U.S. ‘ill-advised’ for Manitoban rate-payers: Pallister
Thursday, Mar. 13, 2014 at 2:08 PM
He said experts to testify at the ongoing PUB hearing will say Hydro’s expectations are overblown.
Filed under Canada permitting, Uncategorized
No, not that kind of scoping, for scoping of the Environmental Report, or is it THIS Environmental Report… whichever, it’s this kind of scoping:
In this case, it’s Environmental Report, or Environmental Report, and not Environmental Impact Statement (that is an issue that should be raised, see below, and the rules pertaining to an EIS in a Certificate of Need proceeding), and they’re looking for what all specifically should be included in this “Environmental Report.”
There’s a “Draft” scoping decision that has the rough outline:
What to submit for comments? Well, it’s got to be specific! They have general categories, and if you have something specific for consideration within these categories, send it in! And if there is an environmental consideration NOT addressed here, send it in!
Some ideas:
And if you’re interested in the Canadian “Independent Expert” report on environmental considerations, and remember, this is for the WHOLE Canadian project:
Filed under Certificate of Need, Environmental Review, PUC Filings
Half of the Great Northern Transmission Project is in Canada, where the transmission line is part of the much larger “Manitoba Hydro’s proposed preferred development plan for the Keeyask and Conawapa Generating Stations, their associated domestic AC transmission facilities and a new Canada-USA transmission interconnection.“
Manitoba Public Utilities Board NFAT site for this project
- start construction of the Keeyask generating station (G.S.) for a 2019 in-service date (ISD)
- proceed with a 250 MW export agreement with Minnesota Power (MP)
- proceed with a 100 MW export agreement with Wisconsin Public Service (WPS)
- proceed with a 750 MW U.S. transmission interconnection
- proceed with a 300 MW export agreement with WPS subject to satisfactory conclusion of negotiations currently still underway.
Intervenors: CLICK HERE for identification and information about their cases
They are going through a similar but MUCH more rigorous process, and the NFAT hearing has just begun, scheduled to extend from Monday’s beginning through May 13, 2014, with “Closing Submissions” following until May 26, and maybe longer than that.
Also, if you go to the “HEARING“ tab, then click on Exhibit Lists, each intervenor’s exhibits are linked, from the initial Intervenor Application to everything they plan to enter during the hearing, and… like… WOW! Lots of good info there, including:
LaCapra – Appendix 8 Transmission (MAJORLY redacted)
LaCapra – Appendix 6 Export Markets (also MAJORLY redacted)
Spend some time on the NFAT site and check out how they conduct hearings up there, what type of evidence and reports they’re entering, the length of the hearings, and check the intervenors’ work plans and the amounts the Manitoba PUB is dishing out for intervenor expenses! Granted the subject of this Canadian hearing is much broader than “just” a transmission line, but what a difference it would make of hearings here were more like hearings there!
Filed under Canada permitting, Uncategorized
Fresh from the Inbox, Minnesota Power has responded to RRANT’s initial Information Requests:
Some will seem repetitive, but I’m just going around the same thing several ways…
The most interesting to me are the links in the response to IR 4 for MISO and other studies to justify or support building the GNTL project, THANK YOU Minnesota Power FOR SENDING WORKING LINKS:
System Impact Study (SIS) reports and meeting presentations
Draft SIS Report Prior Outage & Injection Analysis 7/9/2010
Draft SIS Report – TO Option 4/26/2010
Additional Impact Analysis Draft Report 4/20/2010
Executive Summary (Final Report) 7/20/2009
Final SIS Report Summer Peak analysis 7/20/2009
Final SIS Report Winter Peak analysis 7/20/2009
Final SIS Report Stability analysis 7/20/2009
Updated Draft Stability SIS Report analysis 6/29/2009
Updated Draft SIS Report- Winter Peak analysis 6/29/2009
Updated Draft SIS Report- Summer Peak analysis 6/29/2009
Draft Stability analysis 4/30/2009
Draft SIS Report- Winter Peak analysis 3/20/2009
Draft SIS Report- Summer Peak analysis 3/11/2009
Draft SIS Report 1/13/2009
Preliminary Draft SIS Report 12/16/2008
LT MH Study Screening results 1/21/2009
MH_TSR_Group Study_Transmission Options 1/21/2009
Facilities Study Reports and meeting presentations
MH-MP_AC_Thermal_Sensitivity_Analysis-Eastern_Plan-Draft_Report-01-07-13.pdf
MH-MP_AC_Thermal_Sensitivity_Analysis-Western_Plan-Draft_Report-01-07-13.pdf
MH-MP TSR meeting Feb 2013 3/6/2013
MH-MP TSR meeting Jan 2013_EPL 1/8/2013
MH-MP AC Thermal Sensitivity Analysis – Draft Report – 01-03-2013 1/8/2013
Dorsey – Iron Range 500 kV Project Preliminary Stability Analysis – Draft Report – 12-5-2012 1/8/2013
MH Group Study Option 1 FS 6/1/2010
MH Group Study CapX – TO presentation 11/4/2009
CapX FS proposal presentation 11/4/2009
Additional Analysis Scope document 11/4/2009
Final FS Report (GRE) 1/19/2010
Filed under Information Requests, Need, PUC Filings, Uncategorized