Half of the Great Northern Transmission Project is in Canada, where the transmission line is part of the much larger “Manitoba Hydro’s proposed preferred development plan for the Keeyask and Conawapa Generating Stations, their associated domestic AC transmission facilities and a new Canada-USA transmission interconnection.“
Manitoba Public Utilities Board NFAT site for this project
- start construction of the Keeyask generating station (G.S.) for a 2019 in-service date (ISD)
- proceed with a 250 MW export agreement with Minnesota Power (MP)
- proceed with a 100 MW export agreement with Wisconsin Public Service (WPS)
- proceed with a 750 MW U.S. transmission interconnection
- proceed with a 300 MW export agreement with WPS subject to satisfactory conclusion of negotiations currently still underway.
Intervenors: CLICK HERE for identification and information about their cases
They are going through a similar but MUCH more rigorous process, and the NFAT hearing has just begun, scheduled to extend from Monday’s beginning through May 13, 2014, with “Closing Submissions” following until May 26, and maybe longer than that.
Also, if you go to the “HEARING“ tab, then click on Exhibit Lists, each intervenor’s exhibits are linked, from the initial Intervenor Application to everything they plan to enter during the hearing, and… like… WOW! Lots of good info there, including:
LaCapra – Appendix 8 Transmission (MAJORLY redacted)
LaCapra – Appendix 6 Export Markets (also MAJORLY redacted)
Spend some time on the NFAT site and check out how they conduct hearings up there, what type of evidence and reports they’re entering, the length of the hearings, and check the intervenors’ work plans and the amounts the Manitoba PUB is dishing out for intervenor expenses! Granted the subject of this Canadian hearing is much broader than “just” a transmission line, but what a difference it would make of hearings here were more like hearings there!