So, from SNL Financial, LLC:

Transmission line developer, DOE pilot more open siting strategy

Tuesday, May 19, 2015 1:45 PM ET

By Esther Whieldon

The Department of Energy and the developer of the 500-kV Great Northern Transmission Line from Minnesota to Canada are piloting a potential new federal process for siting grid projects that they believe is key to preventing the kinds of delays that have plagued some other projects. Their plan: work out most of the kinks through stakeholder meetings and joint agency discussions before the developer files an application.

A pre-application process is not a new concept. Hydropower project and natural gas pipeline developers go through a pre-application process at FERC, for example. However, there is no formal pre-application process at the federal level for high-voltage transmission projects.

Large, multistate transmission lines, particularly those that require approvals from more than one federal agency, often take between five and 10 years to complete. Construction can take as little as two years, but getting all the necessary permits and approvals from the federal government, state regulators and local permitting authorities can take five years or more. President Barack Obama and the DOE have tried to accelerate these timelines but with minimal success.

The DOE in 2013 sought public input on whether a voluntary transmission project pre-application process would be useful. Electricity trade groups and some others gave the idea a thumbs down, arguing the process would be fraught with timing and redundancy issues that would deter developers from using it.

One developer, however, ALLETE Inc. subsidiary Minnesota Power Inc., has adopted the general concept of a pre-application process for its Great Northern Transmission line and officials from the utility and the DOE are now touting the effort as a success, thus far.

About two years before Minnesota Power filed applications for the project, the utility reached out to the department and other agencies and started holding public stakeholder meetings to narrow down the scope of its proposal and avoid areas that are likely to draw local opposition. The utility started with a study area covering about a quarter of Minnesota and, through consultation with stakeholders in more than 70 public meetings, narrowed the project route down to about 220 miles, said Minnesota Power senior attorney David Moeller. Also, the DOE in late 2012 arranged a multi-agency meeting with Minnesota Power on the project. It is “really kind of unheard of to have that type of engagement before we even filed a permit application,” Moeller said in an interview.

Early stakeholder engagement has become even more valuable following the advent of social media, which project opponents have wielded to coordinate their efforts. “People have a lot of different platforms to communicate their support or opposition,” said Amy Rutledge, spokeswoman for ALLETE.

“Traditionally you can draw a line and say that looks like a good area but, until you talk to people and agencies, you don’t know what’s happening on the ground and what the best opportunities and constraints are for developing large transmission projects,” Moeller said.

To avoid duplication, the DOE and the Minnesota Department of Commerce also agreed to prepare a joint environmental impact statement on the project, according to the energy department’s website for the project. The Minnesota Public Utilities Commission uses the commerce department’s analysis in reviewing the project.

Projects of a size similar to the Great Northern line typically take about three to four years to get through the federal process, Moeller said. And while the total time Minnesota Power will have dedicated to the project is expected to fall within that range, the application process itself should take only about a year and a half, Moeller said.

The Minnesota PUC on May 14 approved a certificate of need for the Great Northern Project, which is expected to cost up to $710 million in 2013 dollars, according to a Minnesota Power press release. Hearings on Minnesota Power’s pending route permit application at the PUC are scheduled for July and August. Also pending is the DOE’s decision on a presidential permit for the project, which is required for projects that cross into another country.

The DOE and the White House have at least twice in the last year pointed to the Great Northern Project as the poster child for improving the transmission siting process. In its quadrennial energy review in April, the department noted it is piloting its idea for a pre-application process through the proposed Great Northern Transmission Line.

Among other things, the DOE initiated monthly meetings with other federal agencies, the project developer and other non-federal entities to “ensure early coordination,” the White House said in a May 2014 infrastructure siting fact sheet. For its part, Minnesota Power held more than 70 public meetings, according to Rutledge and Moeller.

“Through these early coordination meetings, the company was able to narrow down potential corridors to two routes in their application which address agency concerns and will facilitate a more efficient review process,” the White House said.

The DOE declined to comment.

About the Great Northern Transmission Line

The Great Northern Transmission Line is planned to span from the U.S.-Canada border to Minnesota Power’s Blackberry Substation near Grand Rapids, Minn. North of the U.S. border, provincial government-owned utility Manitoba Hydro plans to build its portion, called the Manitoba-Minnesota Transmission Project, from a major converter station near Winnipeg to the border.

Initially, Minnesota Power and Manitoba Hydro will split ownership of the U.S. portion of the line, with Minnesota Power owning 51%. Manitoba Hydro will have sole ownership of the Canadian portion of the line. In addition to Minnesota Power buying hydropower from Manitoba Hydro, the two utilities have reached a deal under which Minnesota Power can use Manitoba Hydro’s system to store some excess wind energy.

Leave a Comment

Filed under DOE (Dept of Energy), Presidential Permit

Video of PUC GNTL Oral Argument & Deliberation/Decision

Here’s the videos of this week’s Great Northern Transmission Line Oral Argument (May 13, 2015) and Deliberation/Decision (May 14, 2015) at the PUC:

Oral Argument – Wednesday, May 13, 2015

Deliberation/Decision – Thursday, May 14, 2015

And remember this map from the Northern Area Study, where the point is to get electricity from Manitoba through Minnesota, through Wisconsin, and on down towards Detroit — the Minnesota Power “Phase II” from Blackberry sub to Arrowhead (Duluth) sub was cancelled/postponed, so as proposed here, it stops at Blackberry:

Untitled

Leave a Comment

Filed under Certificate of Need, PUC Filings

Deliberation and Decision on GNTL at PUC today!

Right here, right now:

PUC Webcast

ALJ’s Recommendation_20153-108286-01

Staff Briefing Papers_20155-110199-01

Amended Findings of Fact and Decision Options_20155-110407-01

John Tuma as a Commissioner is surprising me, seems he’s really been doing his homework.  And Lipschultz, as always, is raising the right questions and doing some serious thinking.  These last two appointments have been good ones, it seems!

WOW, they’re saying that the calculation has not been done as to whether in the long run it is cheaper to pay Construction Work in Progress (CWIP) or Allowance For Used During Construction (AFUDC).  Then Tuma is noting CWIP is legislation, but it is only an option, not a requirement.  And no-one is noting that the CWIP option came in as part of the 2005 Transmission Bill from Hell.  As LPI notes, CWIP is not a mandate, and the burden of proof is on the Applicants to demonstrate that it is just and reasonable.  Moeller/MP claims it will be an additional $55 million for AFUDC rather than CWIP (and whines about harm to the company).  Moeller DOES admit that the CWIP legislation incentives transmission, DOH!

Heydinger is wanting to modify the ALJ’s Recommendation, to take out some “editorial” comments.  Strike paragraph 316 regarding “rate shock” and alter first part of FOF 317 about whether requiring AFUDC would harm MP…

Commissioner Lange is talking about approving CoN, that Commerce confirmed the load forecast, and that the Commission has had to revise prior decisions and that she takes that to heart.  Also takes into account the question of Manitoba Hydro’s interest.

Tuma also raises the needs of MP and its customers, and noted legislature wants us to think regionally, and that we’re mandated to figure it out.

Commissioner Wergin is not all that concerned about regional, they’ve been a good neighbor, they’re part of MISO.  And later, I’m amazed at how smooth the end result has been… I think that the company has followed through with informing the public… that has a lot to do with how smooth this has gone.

… sigh…

Certificate of Need approved.