Coming up W & Th — DOE holds public hearings

Comments on the Draft Environmental Impact Statement are due Monday, August 10, 2015.  

This week the DOE’s Public Hearings (and Commerce “Meetings”) begin on the DEIS for the Presidential Permit and route for the Great Northern Transmission Project.

Here’s the schedule:

DEIS Public Hearings

And here’s the DEIS that we’re supposed to read up on and comment about — from the DOE’s site:

Comments are due Monday, August 10, 2015.  

Send comments to Comments on the Draft EIS to Julie Smith at the address or email above or by fax to (202) 586–8008, or to William Storm at the address or email below.  Be sure to write the PUC docket number TL-14-21 and the DOE number EIS-0499 on all comments.

Julie Ann Smith, PhD, Electricity Policy Analyst
DOE NEPA Document Manager
National Electricity Delivery Division (OE-20)
U.S. Department of Energy
1000 Independence Avenue SW
Washington, DC 20585

JulieA.Smith@hq.doe.gov

+++++++++++++++++

William Cole Storm, Environmental Review Manager
Energy Environmental Review and Analysis
85 7th Place East, Suite 500
Saint Paul, Minnesota 55101

bill.storm@state.mn.us

Leave a Comment

Filed under DOE (Dept of Energy), Environmental Review, Presidential Permit, Routing Docket

Leave a Reply